logo
Workcode & Project Details
Work Code Number : 003-10-N-G-E-R-IM-006
Name of the Project : Improvements Roads at Ashoknagara in Bagalgunte Sub-Division
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2500000
Workcode Approval Date : 00-00-0000 Approved Cost : 2677500
Work Order Date : 10-09-2009 Expenditure Incurred : 2675421
Client Name : Approved Cost in Percentage : 0.071
Location Details
District : Constituency : Dasarahalli
Zone : Dasarahalli Department Type :
Division : T-Dasarahalli Sub Division : T-Dasarahalli
Ward Name : Bagalagunte Ward No : 14
Locality : Postal Code :
Area : Ashoknagara
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : POW
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : JC/DZ/AS/165/09-10  29-06-2009
Technical Sanction No and Date : CE/Z/TS/259/09-10/  23-07-2009
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(DASARAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : N Khneera naik
Designation : Executive Engineer
User ID : 36101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Gopalappa
Designation : AEE
User ID : 3610102
Mobile Number :
Email Id :
Ward Engineer
Name : Ravindra
Designation : Assistant Engineer
User ID : 361010201
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 10-09-2009 Probable Date of completion :10-09-2009
Scheduled date of completin as per contract : 09-12-2009 Actual Date of Completion : 31-10-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Work Completed
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 26-06-2024 22:55:24