Workcode & Project Details
Work Code Number : 000-09-N-G-0-B-RH-009
Name of the Project : Instaling Roof Top Rain Water Harvesting System at BBMP Office Building Chennammanakere Banashankari.
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 448000
Workcode Approval Date : 00-00-0000 Approved Cost : 542000
Work Order Date : 05-11-2008 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 5.42
Location Details
District : Constituency : Basavanagudi
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : 12-Urban Forestry & Environment Management - Water Management.
Scheme :
Amount Alloted :
Administrative Approval No and Date : PSR(G)-302/08  00-00-0000
Technical Sanction No and Date : EE-3/(P-2)/07/08-09  00-00-0000
Technical Notification No and Date : EE-3/(P-2)/TEND/112//08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Projects-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Ganga Hanumaiah
Designation : Executive Engineer
User ID : 21102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Keshava murthy. K.R
Designation : AEE
User ID : 2110203
Mobile Number :
Email Id :
Ward Engineer
Name : Shekarappa.S
Designation : Assistant Engineer
User ID : 211020304
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 3 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :05-11-2008
Commencement Date : 07-11-2008 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 04-02-2009 Actual Date of Completion : 04-02-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Completed
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 09-06-2024 00:35:02