logo
Workcode & Project Details
Work Code Number : 205-09-N-J-N-D-FO-002
Name of the Project : Construction of RCC Bridge across V.Valley near Kodipalya Vidyapeeta at Kengeri in Rajarajeshwarinagara
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 30000000
Workcode Approval Date : 00-00-0000 Approved Cost : 0
Work Order Date : 23-09-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Yeshwanthpura
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Rajarajeshwarinagara
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 1092/2008-09  00-00-0000
Technical Sanction No and Date : CE/SWD/89/2008-09  00-00-0000
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-1
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri Shiva Kumar S.
Designation : Executive Engineer
User ID : 24101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri.Mahantesh.D.R
Designation : AEE
User ID : 2410101
Mobile Number :
Email Id :
Ward Engineer
Name : Sri. Krishne Gowda
Designation : Assistant Engineer
User ID : 241010101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :31-03-2010
Scheduled date of completin as per contract : 00-00-0000 Actual Date of Completion : 00-00-0000
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Pier,abutments and Right side Retaiining wall completed
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 18-06-2024 02:02:54