Workcode & Project Details
Work Code Number : 000-08-N-J-N-D-FO-047
Name of the Project : Construction of all Civil works erecting commissing of STP of 250-KLD capacity including all elecrical works by side of V.Valley V-200 near Krishanandangr in VVP-4
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 6556000
Workcode Approval Date : 00-00-0000 Approved Cost : 6556000
Work Order Date : 19-07-2008 Expenditure Incurred : 4474000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Rajarajeshwari Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Krishananda Nagara
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE(SWD)/ADMIN/241/2008-09  00-00-0000
Technical Sanction No and Date : CE(SWD)/Tech-san/08/2008-09  00-00-0000
Technical Notification No and Date : EE/SWD/VV/Tend/14/2007-08  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri Gurudutt .P.
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri Ravishankar R.S
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri Prakash S.B
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :19-07-2007
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 18-09-2008 Actual Date of Completion : 04-05-2009
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Due to public protest the site could not be handed over(extra EIRL has to be sanction)
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 18-06-2024 04:41:18