logo
Workcode & Project Details
Work Code Number : 064-10-M-G-T-B-EF-01
Name of the Project : Providing gril to the Power Room & providing Pumpset with necessary cable etc. to the existing sump at Dr. B.R. Ambedkar Stadium at A.D. Halli
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 300000
Workcode Approval Date : 00-00-0000 Approved Cost : 300000
Work Order Date : 15-07-2009 Expenditure Incurred : 315000
Client Name : Approved Cost in Percentage : 3.29
Location Details
District : Constituency : Govindraja Nagar
Zone : South Department Type :
Division : Govindraja Nagar Sub Division : Govindraj Nagar
Ward Name : Govindraja Nagara Ward No : 104
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : S.R 2007-2008
Budget Category(Head of Account) : Maintenance Works
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 48/75  00-00-0000
Technical Sanction No and Date : 48/193  00-00-0000
Technical Notification No and Date : EE/ELE/TN/GL/02/2009-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(SOUTH)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri. K. Govindaiah
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri. Puttalingaiah
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri. Ramesh .D
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 3 (Electrical) Contractor Name : Srinivas.K.B M/s Srinag Electricals
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :15-08-2009
Scheduled date of completin as per contract : 15-08-2009 Actual Date of Completion : 27-11-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 28-09-2024 05:09:47