Workcode & Project Details
Work Code Number : 123-10-N-G-E-B-FO-002
Name of the Project : Providing and construction of contact point 2 no's(Chennammana kere Achukatta) Ramarao layout in old no-54/ new ward no-123
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 0
Workcode Approval Date : 00-00-0000 Approved Cost : 0
Work Order Date : 00-00-0000 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Padmanabha Nagar
Zone : South Department Type :
Division : Padmanabha Nagar Sub Division : Padmanabha Nagar
Ward Name : Padmanabha Nagar Ward No : 182
Locality : Postal Code :
Area : Chennammana kere Achukatta
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : POW GRANTS 2009-10
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE(S)ADMN/APPL/115/223/09-10  00-00-0000
Technical Sanction No and Date : CE(S)TS/NO.100&101/221/09-10  00-00-0000
Technical Notification No and Date : TEND/01/2009-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(SOUTH)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : N .R Srikantaiah gowda
Designation : Executive Engineer
User ID : 33103
Mobile Number :
Email Id :
Sub-Division Engineer
Name : L.KENCHAPPA
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : MANJE GOWDA
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 00-00-0000 Actual Date of Completion : 00-00-0000
Work Status : Work In Progress Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : WORK IN PROGRESS
Category Details
Category : Type of Work : Sub Work :