Workcode & Project Details
Work Code Number : 056-08-I-G-E-R-IM-004
Name of the Project : IMPROVEMENTS TO FOOTPATH AT 9TH MAIN FROM POST OFFICE TO 13TH CROSS IN WARD 56
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 218380
Workcode Approval Date : 00-00-0000 Approved Cost : 218380
Work Order Date : 04-04-2008 Expenditure Incurred : 2000000
Client Name : Approved Cost in Percentage : 10.52
Location Details
District : Constituency : Padmanabha Nagar
Zone : South Department Type :
Division : Padmanabha Nagar Sub Division : Padmanabha Nagar
Ward Name : Padmanabha Nagar Ward No : 182
Locality : Postal Code :
Area : 9TH MAIN FROM POST OFFICE WARD 56
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : ZONAL WORKS
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : EE/BG2/AA/107/07-08  00-00-0000
Technical Sanction No and Date : EE/BG2/TS/189/07-08  00-00-0000
Technical Notification No and Date : EE/BG2/TEND/14/07-08  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(SOUTH)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : N .R Srikantaiah gowda
Designation : Executive Engineer
User ID : 33103
Mobile Number :
Email Id :
Sub-Division Engineer
Name : MOHANLAL SUKHADIYA
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : JAYARAM
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :08-04-2009
Commencement Date : 00-00-0000 Probable Date of completion :03-07-2008
Scheduled date of completin as per contract : 03-07-2008 Actual Date of Completion : 22-07-2008
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : WORK COMPLETED
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 26-06-2024 20:20:26