Workcode & Project Details
Work Code Number
: 054-09-M-S-E-D-IM-005
Name of the Project
: Improvements to drain culverts flagging course & covering slab to drain at 3rd main road Srinivasnagar in ward - 54
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 2728000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 2728000
Work Order Date
: 19-02-2009
Expenditure Incurred
: 0
Client Name
:
Approved Cost in Percentage
: 9.99
Location Details
District
:
Constituency
: Padmanabha Nagar
Zone
: South
Department Type
:
Division
: Padmanabha Nagar
Sub Division
: Padmanabha Nagar
Ward Name
: Padmanabha Nagar
Ward No
: 182
Locality
:
Postal Code
:
Area
: Srinivasnagar
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
:
Budget Category(Head of Account)
:
Scheme
: No Scheme
Amount Alloted
:
Administrative Approval No and Date
: AC(S)/ADMN/APPL/48/194/08-09 00-00-0000
Technical Sanction No and Date
: CE(S)TS/189/295/08-09 00-00-0000
Technical Notification No and Date
: EE BG-2/DM/03/08-09 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: C.E(SOUTH)
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: N R Srikantaiah Gowda
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: L. Kenchappa
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: ManjeGowda
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
:
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:00-00-0000
Commencement Date
: 00-00-0000
Probable Date of completion
:00-00-0000
Scheduled date of completin as per contract
: 20-05-2009
Actual Date of Completion
: 00-00-0000
Work Status
: Work In Progress
Spill Over / Programme of Work and Year
: Programme of Work
Percentage of Physical Progress
: 0
Remarks
: Work in progress
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 28-09-2024 03:41:22