Work Code Number : 201-08-N-G-H-P-MI-012
Name of the Project : PROVIDING CHILDREN EQUIPMENT TO THE PARK AT KODI CHIKKANAHALLI ROTARY NAGARA GOVT HOSPITAL PREMISES. (CHANGE OF PLACE AS MENTIONED ABOVE).
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 537000
Workcode Approval Date : 00-00-0000 Approved Cost : 537000
Work Order Date : 20-09-2008 Expenditure Incurred : 537000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Bommanahalli
Zone : Bommanahalli Department Type :
Division : Bommanahalli Sub Division : HSR Layout
Ward Name : HSR Layout Ward No : 174
Locality : Postal Code :
Area : HSR LAYOUT SECTOR-1
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : APPROVED RATE BY CE(S)
Budget Category(Head of Account) : JANOODYANA PARKS
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : JC/B/BBMP/PR/10/08-09  00-00-0000
Technical Sanction No and Date : EE/B/DM/TS/47/08-09  00-00-0000
Technical Notification No and Date : BBMP/HS(BZ)/TEND/PR/19/08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE (BOMMANAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : EE. (Bommanahalli)
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : ANANDA B.C.
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : ATHIKUR REHMAN IDRUS
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :29-10-2008
Commencement Date : 00-00-0000 Probable Date of completion :19-10-2008
Scheduled date of completin as per contract : 19-10-2008 Actual Date of Completion : 00-00-0000
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :