Workcode & Project Details
Work Code Number
: 202-09-N-G-H-P-MI-010
Name of the Project
: Constn. of Gozebo to park between 17th and 19th B cross 16th B cross B sector etc
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 2171000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 2171000
Work Order Date
: 30-08-2008
Expenditure Incurred
: 2169000
Client Name
:
Approved Cost in Percentage
: -0.98
Location Details
District
:
Constituency
: Yelahanka
Zone
: Yelahanka
Department Type
:
Division
: Yelahanka
Sub Division
: Yelahanka Satellite Town
Ward Name
: Yelahanka Satellite
Ward No
: 4
Locality
:
Postal Code
:
Area
: Yelahanka
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2007-08
Budget Category(Head of Account)
: Horticulture park
Scheme
: No Scheme
Amount Alloted
: Non Budgeted
Administrative Approval No and Date
: 35/08-09 00-00-0000
Technical Sanction No and Date
: 11-08-2009
Technical Notification No and Date
: EE (P)/TEND/14/08-09 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: C.E(YALAHANKA)
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: B.S.Prahallad
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: R.BadariNarayana
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: K.G.Sundresh
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
:
Contractor Name
:
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:30-08-2008
Commencement Date
: 00-00-0000
Probable Date of completion
:00-00-0000
Scheduled date of completin as per contract
: 29-11-2008
Actual Date of Completion
: 05-03-2009
Work Status
: Completed
Spill Over / Programme of Work and Year
: Spill Over
Percentage of Physical Progress
: 0
Remarks
:
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 26-06-2024 09:18:32