Work Code Number : 201-09-N-G-E-R-CD-005
Name of the Project : PROVIDING AND FIXING SIDE DRAINSCONSTRUCTION OF CULVERTSASPHALTING TO TRANSFORMER FACTORY ROAD TWO ADJACENT ROADS IN SARJAPUR ROAD IN AMBLIPURA VILLAGE
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 3014000
Workcode Approval Date : 00-00-0000 Approved Cost : 3014000
Work Order Date : 29-12-2008 Expenditure Incurred : 1504000
Client Name : Approved Cost in Percentage : 24.08
Location Details
District : Constituency : Mahadevapura
Zone : Mahadevapura Department Type :
Division : Mahadevapura Sub Division : Marathahalli
Ward Name : Bellandur Ward No : 150
Locality : Postal Code :
Area : AMBLIPURA VILLAGE
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : ROADS AND DRAINS
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 37/08-09  00-00-0000
Technical Sanction No and Date : 92/08-09  00-00-0000
Technical Notification No and Date : EE.[BH]/TEND/11/2008-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(MAHADEVAPURA)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : SEVYA NAIK
Designation : Executive Engineer
User ID : 38102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : B.M.RAMAMUTHY
Designation : AEE
User ID : 3810203
Mobile Number :
Email Id :
Ward Engineer
Name : A.RAVINDRABABU
Designation : Assistant Engineer
User ID : 381020304
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name : Suresh.P.R
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :29-12-2008
Commencement Date : 29-12-2008 Probable Date of completion :31-07-2010
Scheduled date of completin as per contract : 28-03-2009 Actual Date of Completion : 00-00-0000
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : LAND OWNERS ROAD LITIGATION