logo
Workcode & Project Details
Work Code Number : 000-04-N-G-P-R-IM-004
Name of the Project : Provding Asphaltig to Lazzer road in ward No 85 attached to ITC ROB(under project east)
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 4052000
Workcode Approval Date : 00-00-0000 Approved Cost : 4052000
Work Order Date : 12-01-2009 Expenditure Incurred : 3025000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : C.V.Raman Nagar
Zone : East Department Type :
Division : C.V.Raman Nagar Sub Division : C.V.Raman Nagar
Ward Name : Sarvagna Nagar Ward No : 79
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : Pwd 2007-08 &NHSR 2007-08
Budget Category(Head of Account) : ITC ROB attached
Scheme :
Amount Alloted :
Administrative Approval No and Date :   00-00-0000
Technical Sanction No and Date : CE/P/TS/47/08-09  00-00-0000
Technical Notification No and Date : EE/P/E/Tend/03/08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(EAST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri.P.Vishwanath
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri.V.Ravindra
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri.M.C.Prabhusharan
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :12-01-2009
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 16-03-2009 Actual Date of Completion : 08-03-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 26-06-2024 09:16:49