Work Code Number : 053-10-N-G-E-R-CO-006
Name of the Project : Providing CC road from Temple road (1st main road) to 10th cross road to SWD in MLM in W-53.
Short Name of Project :Providing CC road
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 1600000
Workcode Approval Date : 00-00-0000 Approved Cost : 1600000
Work Order Date : 29-08-2009 Expenditure Incurred : 1691000
Client Name : Approved Cost in Percentage : 8
Location Details
District : Constituency : Gandhi Nagar
Zone : West Department Type :
Division : Gandhi Nagar Sub Division : Gandhi Nagar
Ward Name : Dattathreya Temple Ward No : 77
Locality : Postal Code :
Area : 10th Cross MLM
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : POW 2009-10
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : Admn/148/09-10  00-00-0000
Technical Sanction No and Date : TS/159/09-10  00-00-0000
Technical Notification No and Date : EE(MLM)/TEND/E-01/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E.(WEST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : R.Idayavendon
Designation : Executive Engineer
User ID : 32102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : K.B.Jayannagowda
Designation : AEE
User ID : 3210201
Mobile Number :
Email Id :
Ward Engineer
Name : D.Harish kumar
Designation : Assistant Engineer
User ID : 321020101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 29-10-2009 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  2008-2009
Percentage of Physical Progress : 100 Remarks :