Workcode & Project Details
Work Code Number
: 17-10-M-G-E-D-IM-008
Name of the Project
: Construction of culverts & Improvements to side drains in 1st main of R.K. Garden in ward no.4
Short Name of Project
:Construction of culverts & Improvements
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 1000000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 1099000
Work Order Date
: 22-08-2009
Expenditure Incurred
: 1099000
Client Name
:
Approved Cost in Percentage
: 9.99
Location Details
District
:
Constituency
: Malleshwaram
Zone
: West
Department Type
:
Division
: Malleshwaram
Sub Division
: Mathikere
Ward Name
: Mathikere
Ward No
: 36
Locality
:
Postal Code
:
Area
: Mathikere
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2009-10
Budget Category(Head of Account)
: ADDITIONAL GRANTS 2008-09
Scheme
: No Scheme
Amount Alloted
: Non Budgeted
Administrative Approval No and Date
: EE(MLM)AE/Admn/176/09-0 00-00-0000
Technical Sanction No and Date
: TS/EE/(MLM)/AE/176/09-10 00-00-0000
Technical Notification No and Date
: EE/MLM/AE/TEND/GL-19/08-09 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: C.E.(WEST)
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: B.G. Prakash Kumar
Designation
: Executive Engineer
User ID
: 32101
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Y.M. Muniraju
Designation
: AEE
User ID
: 3210102
Mobile Number
:
Email Id
:
Ward Engineer
Name
: M.K. Harish
Designation
: Assistant Engineer
User ID
: 321010202
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
:
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:22-08-2009
Commencement Date
: 22-08-2009
Probable Date of completion
:15-10-2009
Scheduled date of completin as per contract
: 15-10-2009
Actual Date of Completion
: 15-10-2009
Work Status
: Completed
Spill Over / Programme of Work and Year
: Spill Over
Percentage of Physical Progress
: 0
Remarks
:
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 26-06-2024 22:39:58