Workcode & Project Details
Work Code Number
: 019-09-N-S-E-R-AS-003 004 009 010 & 01JOINTCOMMR(W
Name of the Project
: Asphalting to roads between 8th and 10th Main 11th to 15th D Main 2nd A to C Cross of 1st Block 3rd Stage Basaveshwaranagar in Ward No.19.
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 9000000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 9668000
Work Order Date
: 22-08-2009
Expenditure Incurred
: 9668000
Client Name
:
Approved Cost in Percentage
: 8.5
Location Details
District
:
Constituency
: Rajaji Nagar
Zone
: West
Department Type
:
Division
: Rajaji Nagar
Sub Division
: Rajaji Nagar
Ward Name
: Basaveshwara Nagar
Ward No
: 100
Locality
:
Postal Code
:
Area
: Manjunathnagar Basaveshwaranagar
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2008-09
Budget Category(Head of Account)
: G.O.K. Grants - 2008-09
Scheme
: No Scheme
Amount Alloted
:
Administrative Approval No and Date
: JOINTCOMMR(W)/ADMN/07/09-10 00-00-0000
Technical Sanction No and Date
: TS/CE(W)/AE/209/09-10 00-00-0000
Technical Notification No and Date
: EE/RNR/TEND/05/08-09 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: C.E.(WEST)
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: Gurunath
Designation
: Executive Engineer
User ID
: 32103
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Arunkumar
Designation
: AEE
User ID
: 3210301
Mobile Number
:
Email Id
:
Ward Engineer
Name
: H.Shivakumar
Designation
: Assistant Engineer
User ID
: 321030102
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
:
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:23-08-2009
Commencement Date
: 25-08-2009
Probable Date of completion
:22-11-2009
Scheduled date of completin as per contract
: 22-11-2009
Actual Date of Completion
: 31-10-2009
Work Status
: Completed
Spill Over / Programme of Work and Year
: Spill Over
Percentage of Physical Progress
: 0
Remarks
: Completed
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.