Work Code Number : 7A) 054-09-M-S-E-D-IM-012 7B)054-09-N-SCE(S)ADMN/A
Name of the Project : 7A) IMPROVEMENS TO DRAIN CULVERTS COVERING SLAB TO IYYAPPA SWAMY TEMPLE ROAD CT BED TO KATHRIGUPPE MAIN ROAD
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 3202000
Workcode Approval Date : 00-00-0000 Approved Cost : 3202000
Work Order Date : 18-05-2009 Expenditure Incurred : 3202000
Client Name : Approved Cost in Percentage : 12.04
Location Details
District : Constituency : Basavanagudi
Zone : South Department Type :
Division : Basavangudi Sub Division : GiriNagar
Ward Name : Giri Nagar Ward No : 162
Locality : Postal Code :
Area : KATHRIGUPPE
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : KARNATAKA GOVERNMENT 2008-09 BUDJECT
Scheme :
Amount Alloted :
Administrative Approval No and Date : CE(S)ADMN/APPL/50/124/125/2008-09  00-00-0000
Technical Sanction No and Date : CE(S)TS/12/354/355/2008-09  00-00-0000
Technical Notification No and Date : TEND/03/2008-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(SOUTH)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : C.J.CHANDRASHEKAR
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : L.KENCHAPPA
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : L.MANJEGOWDA
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name : Nikhil, Nishal construction (Pvt) Ltd.,
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :08-01-2010
Scheduled date of completin as per contract : 08-01-2010 Actual Date of Completion : 08-01-2009
Work Status : Yet to Start Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :