Agreement No. & Date : 00-00-0000
|
Site Handed Over Date :00-00-0000
|
Commencement Date : 00-00-0000
|
Probable Date of completion :00-00-0000
|
Scheduled date of completin as per contract : 15-10-2009
|
Actual Date of Completion : 15-10-2009
|
Work Status : Work In Progress
|
Spill Over / Programme of Work and Year : Spill Over
|
Percentage of Physical Progress : 0
|
Remarks : As per the letter no,CE(W)/PR/08/05-06,dated 7-4-06 tender were invited but no responce from the contractor. AS per dicussion for held in JC(W) with the HON"ble COMMISIONER on 06-02-2006 . instuction was issue to entrust the work to KLAC.
|