View Details

Workcode & Project Details
Work Code Number : 205-09-I-G-E-R-AS-036
Name of the Project : Asphalting to 4th and 5th main and cross roads of KST
Estimated Cost : 3239000 Approved Cost : 3239000
Expenditure Incurred : 3235000 Approved Cost in Percentage : 9.99
Zone : Rajarajeshwarinagar Chief Engineer : C.E(RAJARAJESHWARINAGAR)
Division : Kengeri Executive Engineer : Umashanker
Sub Division : Kengeri Assistant Executive Engineer : R Srinivas
Ward Name : Kengeri Assistant Engineer : Sarvottam
Contractor Class : Class 1 A (Civil) Contractor Name : Vinod Kumar.B.K
Read More Details...
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 01-05-2024 17:33:39