Estimated Cost : 546000
|
Approved Cost : 546000
|
Expenditure Incurred : 546000
|
Approved Cost in Percentage : 5.46
|
Zone : Mahadevapura
|
Chief Engineer : C.E(MAHADEVAPURA)
|
Division : K.R.Puram
|
Executive Engineer : M.Venugopal
|
Sub Division : HoraMavu
|
Assistant Executive Engineer : RRajagopalaReddy
|
Ward Name : Vijinapura
|
Assistant Engineer : Jayaprakash.B
|
Contractor Class : Class 1 A (Civil)
|
Contractor Name : Raju.S.K
|