Estimated Cost : 4500000
|
Approved Cost : 4500000
|
Expenditure Incurred : 4418000
|
Approved Cost in Percentage : 45
|
Zone : Head Office
|
Chief Engineer : CE SWD-1
|
Division :
|
Executive Engineer : H Nagendrappa
|
Sub Division :
|
Assistant Executive Engineer : SIDLABASAPPA A
|
Ward Name :
|
Assistant Engineer : Jagadisha B R
|
Contractor Class : Class 1 B (Civil)
|
Contractor Name : Chandrashekar G Prop Sri Sai Charan Constroctiors
|