View Details

Workcode & Project Details
Work Code Number : 000-06-N-H-N-D-SM-001
Name of the Project : Remodelling of Primary & Secondary drain Storm Water Drain in Vrishabhavathi Valley Package-2
Estimated Cost : 241430000 Approved Cost : 0
Expenditure Incurred : 90690000 Approved Cost in Percentage : 25.12
Zone : Head Office Chief Engineer : CE SWD-1
Division : Executive Engineer : Sri M.L.Munikrishna & Shivakumar
Sub Division : Assistant Executive Engineer : Sri Ravishankar R.S
Ward Name : Assistant Engineer : Sri K.Mohan Swamy
Contractor Class : Class 1 A (Civil) Contractor Name :
Read More Details...
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 25-04-2024 11:12:34