View Details

Workcode & Project Details
Work Code Number : 000-07-N-Z-I-D-FO-016
Name of the Project : Construction of SWD including RCC/SSM Retaining walls CD works and other allied works from Ullal Main road to Subhashnagar Tank in RR Zone-4
Estimated Cost : 29000000 Approved Cost : 47224000
Expenditure Incurred : 40211000 Approved Cost in Percentage : 63.31
Zone : Head Office Chief Engineer : CE SWD-2
Division : Executive Engineer : Sri Shivakumar S.
Sub Division : Assistant Executive Engineer : Sri Mahanthesh.D.R
Ward Name : Assistant Engineer : Sri Suresh A.H
Contractor Class : Class 1 A (Civil) Contractor Name :
Read More Details...
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 25-04-2024 12:16:55