Workcode & Project Details
Work Code Number : 304-13-000142
Name of the Project : Construction of Signal Free Corridor along Identified Stretches of Road from Vellara Junction to Hope Farm Junction (via Old Airport Road, Kundalahalli and Whitefield) in Bangalore City (on Lump Sum Turnkey Basis)
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 1352500000
Workcode Approval Date : 00-00-0000 Approved Cost : 1095000000
Work Order Date : 19-02-2014 Expenditure Incurred : 361868500
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency :
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code : 560002
Area : Old Airport Road
Approval Details
Approved By : G. O No: UDD 356 MNY 2012
Year of SR Adopted for Preparation of Estimate : 2011-12
Budget Category(Head of Account) : P 2159
Scheme : Nagarothana
Amount Alloted : Budgeted
Administrative Approval No and Date : G. O No: UDD 356 MNY 2012  10-07-2012
Technical Sanction No and Date : CE(RI)/TS/30/2012-13  21-02-2013
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Projects-Central
Designation : Chief Engineer
User ID :
Mobile Number : 9480684990
Email Id :
Division Engineer
Name : Basavaraj R Kabade
Designation : Executive Engineer
User ID : 0
Mobile Number : 9739625025
Email Id : bbmpeetec@gmail.com
Sub-Division Engineer
Name : Eshwarappa
Designation : AEE
User ID : 0
Mobile Number : 9480683070
Email Id : esh_a@rediffmail.com
Ward Engineer
Name : N I Badiger Devaraju Y
Designation : Assistant Engineer
User ID : 0
Mobile Number : 9972078665,9964578777
Email Id : nibgdg@gmail.com, devaraju.y@gmail.com
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : M/s RNS Infrastructure Limited
Work Status Details
Agreement No. & Date : EE/TEC/AG/22/2013-14  19-02-2014 Site Handed Over Date :11-07-2014
Commencement Date : 11-07-2014 Probable Date of completion :11-07-2016
Scheduled date of completin as per contract : 18-08-2015 Actual Date of Completion : 18-08-2015
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  2015-16
Percentage of Physical Progress : 40 Remarks : Signal Free Corridor from ASC Centre to Hope Farm Junction is taken up under GoK Nagarothana Scheme
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 09-05-2024 01:46:27