logo
Workcode & Project Details
Work Code Number : 132-10-N-E-E-R-AS-009
Name of the Project : Providing Asphalting to D group layout Chandrashekar layout Annapurneshwari nagar layout main roads and cross roads
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 4950000
Workcode Approval Date : 00-00-0000 Approved Cost : 31510000
Work Order Date : 22-08-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Bommanahalli
Zone : Bommanahalli Department Type :
Division : Bommanahalli Sub Division : HSR Layout
Ward Name : Mangammanapalya Ward No : 190
Locality : Postal Code :
Area : Rajarajeshwari Nagar Zone
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) :
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE/RRN/AS/37/09-10  00-00-0000
Technical Sanction No and Date : CE/RRN/TS/69/09-10  00-00-0000
Technical Notification No and Date : BBMP/RRN/EE(P)/TND/03/09-10   05-06-2009
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE (BOMMANAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : S.N.Parasuramegowda
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : M G Ram Mohan
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Puttaraju
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Vinod Kumar.B.K
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :22-08-2009
Commencement Date : 00-00-0000 Probable Date of completion :21-02-2010
Scheduled date of completin as per contract : 21-02-2010 Actual Date of Completion : 30-09-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 05-05-2024 19:44:44