logo
Workcode & Project Details
Work Code Number : 203-09-I-G-V-U-RE-001
Name of the Project : Repairs to UGD Pipe Line in 13 Sub-Division
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 1000000
Workcode Approval Date : 00-00-0000 Approved Cost : 1095845
Work Order Date : 23-12-2008 Expenditure Incurred : 1095400
Client Name : Approved Cost in Percentage : 0.0998
Location Details
District : Constituency : Dasarahalli
Zone : Dasarahalli Department Type :
Division : T-Dasarahalli Sub Division : T-Dasarahalli
Ward Name : T-Dasarahalli Ward No : 15
Locality : Postal Code :
Area : 13
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : Spill over
Scheme : No scheme
Amount Alloted :
Administrative Approval No and Date : EE/DZ/AS/06/08-09   20-06-2008
Technical Sanction No and Date : EE/Z/TS/06/08-09  00-00-0000
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(DASARAHALLI)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri. Parameshwar M.L
Designation : Executive Engineer
User ID : 36101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri. G.H Shanmughappa
Designation : AEE
User ID : 3610102
Mobile Number :
Email Id :
Ward Engineer
Name : Sri. M.C Venkateshiah
Designation : Assistant Engineer
User ID : 361010202
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name : Venkatesh.G
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 23-12-2008 Probable Date of completion :23-12-2008
Scheduled date of completin as per contract : 19-05-2009 Actual Date of Completion : 04-03-2009
Work Status : Completed Spill Over / Programme of Work and Year : POW  
Percentage of Physical Progress : 0 Remarks : 1
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 03-05-2024 01:18:50