Work Code Number : 201-08-N-G-H-P-PL-013
Name of the Project : Raising of 5'x8' PBSeedlings for 50000 during the year 2007-08 BLK-I Bommanahalli Zone
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 85000
Workcode Approval Date : 00-00-0000 Approved Cost : 98000
Work Order Date : 16-06-2008 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 15
Location Details
District : Constituency : Yelahanka
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : Development of lakes in New Zone (Page No. 65) ‚ 
Scheme :
Amount Alloted :
Administrative Approval No and Date : PSR/G/6263/07-08  00-00-0000
Technical Sanction No and Date : EE-3/(P-2)/63/07-08  00-00-0000
Technical Notification No and Date : EE-3/(P-2)/TEND/14/08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Projects-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Gangahanumaiah
Designation : Executive Engineer
User ID : 21102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Keshava murthy. K.R
Designation : AEE
User ID : 2110203
Mobile Number :
Email Id :
Ward Engineer
Name : Venkateshappa.C
Designation : Assistant Engineer
User ID : 211020303
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Others Contractor Name : Narayanaswamy.R
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :16-06-2008
Commencement Date : 18-06-2008 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 30-10-2008 Actual Date of Completion : 30-10-2008
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Completed