Workcode & Project Details
Work Code Number
: 000-10-N-P-P-L-FE-008
Name of the Project
: Providing chain link mesh fencing to chikka bellandur Haralur kere Dommasandra Haralakunate Basapura kere-1 Konappan agrahara Dodda kanahalli Kaggadasapura
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 0
Workcode Approval Date
: 00-00-0000
Approved Cost
: 46500000
Work Order Date
: 06-05-2010
Expenditure Incurred
: 0
Client Name
:
Approved Cost in Percentage
: 0
Location Details
District
:
Constituency
: Mahadevapura
Zone
: Head Office
Department Type
:
Division
:
Sub Division
:
Ward Name
:
Ward No
:
Locality
:
Postal Code
:
Area
:
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2009-10
Budget Category(Head of Account)
: JNNURM
Scheme
:
Amount Alloted
:
Administrative Approval No and Date
: 307/09-10 00-00-0000
Technical Sanction No and Date
: CE/P-2/TS-25/2009-10 00-00-0000
Technical Notification No and Date
: CE/P2/Tend/02/09-10 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: CE Projects-2
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: Mr. Chandra Shekar. N. P
Designation
: Executive Engineer
User ID
: 21103
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Mr. Jagannath Rao
Designation
: AEE
User ID
: 2110303
Mobile Number
:
Email Id
:
Ward Engineer
Name
: Mrs. shilpa.K
Designation
: Assistant Engineer
User ID
: 211030301
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
: Sudhakar Paritala
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:00-00-0000
Commencement Date
: 01-06-2010
Probable Date of completion
:00-00-0000
Scheduled date of completin as per contract
: 31-12-2010
Actual Date of Completion
: 31-12-2010
Work Status
: Work Order to be issued
Spill Over / Programme of Work and Year
: POW
Percentage of Physical Progress
: 0
Remarks
: Work Order to be issued
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 04-05-2024 05:21:41