logo
Workcode & Project Details
Work Code Number : 000-10-N-P-P-B-RH-013
Name of the Project : Roof top rain water harvesting Phase-II at Corporation Girls High school Cleave land town
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 276000
Workcode Approval Date : 00-00-0000 Approved Cost : 277000
Work Order Date : 11-01-2010 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 2.77
Location Details
District : Constituency : Shivaji Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2009-10
Budget Category(Head of Account) : 12-Urban Forestry & Environment management- Water Management.
Scheme :
Amount Alloted :
Administrative Approval No and Date : 10362/09  00-00-0000
Technical Sanction No and Date : EE-3(P-2)/12/09-10  00-00-0000
Technical Notification No and Date : BBMP.EE-3(P-2)/TEND/04//09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Projects-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Ganga Hanumaiah
Designation : Executive Engineer
User ID : 21102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Keshava murthy. K.R
Designation : AEE
User ID : 2110203
Mobile Number :
Email Id :
Ward Engineer
Name : Shekarappa.S
Designation : Assistant Engineer
User ID : 211020304
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :11-01-2010
Commencement Date : 11-01-2010 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 12-04-2010 Actual Date of Completion : 12-04-2010
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : WORK UNDER PROGRESS
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 01-05-2024 07:38:46