Work Code Number : 000-09-N-P-P-O-MI-040
Name of the Project : Improvements to Tower and parallel wall and surrounding area for the Development of FP
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 0
Workcode Approval Date : 00-00-0000 Approved Cost : 8874000
Work Order Date : 15-07-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Gandhi Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : P 1791 2008-09
Scheme :
Amount Alloted :
Administrative Approval No and Date : 724/08-09  00-00-0000
Technical Sanction No and Date : CER No 33/08-09  00-00-0000
Technical Notification No and Date : EE1/P2/TEND/347/08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Projects-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Jagannath
Designation : Executive Engineer
User ID : 21103
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Shivalingaiah .N. D.
Designation : AEE
User ID : 2110301
Mobile Number :
Email Id :
Ward Engineer
Name : Jagdisha.L
Designation : Assistant Engineer
User ID : 211030103
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :03-06-2009
Commencement Date : 15-07-2009 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 31-08-2009 Actual Date of Completion : 03-08-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Work completed