Agreement No. & Date : 00-00-0000
|
Site Handed Over Date :00-00-0000
|
Commencement Date : 00-00-0000
|
Probable Date of completion :30-12-2009
|
Scheduled date of completin as per contract : 28-01-2009
|
Actual Date of Completion : 00-00-0000
|
Work Status : Work In Progress
|
Spill Over / Programme of Work and Year : Spill Over
|
Percentage of Physical Progress : 0
|
Remarks : At proposed ramp one shop is given rent from BBMP RO office ,yet to remove, hearing is under process.
|