logo
Workcode & Project Details
Work Code Number : 000/09/N/G/J/R/MD/065
Name of the Project : Constructing High Raised pedestrian Crossing in H.A.L Defence Colony Marathhalli JeevanBhimanagar RamamurthynagarC.V. Raman Nagar Area.
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2425000
Workcode Approval Date : 00-00-0000 Approved Cost : 2848000
Work Order Date : 19-01-2009 Expenditure Incurred : 2848000
Client Name : Approved Cost in Percentage : 17.95
Location Details
District : Constituency :
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : TEC- Different Head
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE(MR)/TA/ADM/136/08-09  00-00-0000
Technical Sanction No and Date : SE(MR)/TS/98/08-09  00-00-0000
Technical Notification No and Date : BBMP/EE(TEC)/Tend/GL-06/2008-09/  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Basavaraj.R.kabade
Designation : Executive Engineer
User ID : 23108
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Ashok.S.D
Designation : AEE
User ID : 2310801
Mobile Number :
Email Id :
Ward Engineer
Name : Devaraj.Y
Designation : Assistant Engineer
User ID : 231080101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 29-01-2009 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 04-03-2009 Actual Date of Completion : 20-04-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 28-04-2024 04:57:21