Workcode & Project Details
Work Code Number : 000/08/N/G/J/R/BB/014
Name of the Project : Construction of Bus Bays at Avalahalli towards Hosakote Avalahalli Towards city Boodigere cross towards Hosakote Boodigere cross Towards city. 
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2320000
Workcode Approval Date : 00-00-0000 Approved Cost : 2743000
Work Order Date : 19-01-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 17.8
Location Details
District : Constituency :
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : Constructions of Bus Bays & Auto Stands
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE(MR0/TA/ADM/27/08-09  00-00-0000
Technical Sanction No and Date : SE(MR)/TS/18 /08-09  00-00-0000
Technical Notification No and Date : BBMP/EE(TEC)/TEND/01/07-08(08-09)  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Basavaraj.R.kabade
Designation : Executive Engineer
User ID : 23108
Mobile Number :
Email Id :
Sub-Division Engineer
Name : S D Ashok
Designation : AEE
User ID : 2310801
Mobile Number :
Email Id :
Ward Engineer
Name : Devaraju Y
Designation : Assistant Engineer
User ID : 231080101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 18-02-2009 Actual Date of Completion : 00-00-0000
Work Status : Yet to Start Spill Over / Programme of Work and Year : Spill over  
Percentage of Physical Progress : 0 Remarks : Due to widening of NH7 by NHAI the work is not executed