logo
Workcode & Project Details
Work Code Number : 000-10-N-P-R-E-AS-051
Name of the Project : Widening and Strengthening of the existing surface of 5th Main Road from O.R.R to 27th Cross Road of HSR Layout
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 15283000
Workcode Approval Date : 00-00-0000 Approved Cost : 15283000
Work Order Date : 00-00-0000 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 1
Location Details
District : Constituency : Bommanahalli
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : HSR Layout Bommanahalli zone
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2009-10
Budget Category(Head of Account) : Arterial and Sub Arterial Roads
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE(MR)/TA/ADM/181/09-10  00-00-0000
Technical Sanction No and Date : CE(MR)/TS/171/09-10  00-00-0000
Technical Notification No and Date : EE(MR-South East)/TEND/01/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri.B.T.Mohankrishna
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri.Ravi
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Smt.Swetha
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Ramesh.M
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 00-00-0000 Actual Date of Completion : 00-00-0000
Work Status : Work In Progress Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 29-04-2024 04:43:34