Work Code Number : 000-09-N-P-E-R-WD-035
Name of the Project : Removal of excavated muck & debris on Sheshadri road from Ch: 850.00 to 1200.00 Mtr. in Bangalore city
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 500000
Workcode Approval Date : 00-00-0000 Approved Cost : 548000
Work Order Date : 06-06-2009 Expenditure Incurred : 548000
Client Name : Approved Cost in Percentage : 9.94
Location Details
District : Constituency : Gandhi Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Sheshadri road
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : P1733
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : EE/RW-1/AA/03/09-10.  00-00-0000
Technical Sanction No and Date : EE/RW-1/TS/03/09-10.  00-00-0000
Technical Notification No and Date : EE/RW-1/TENDER/04/08-09.  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : R.Sevyanaik
Designation : Executive Engineer
User ID : 23201
Mobile Number :
Email Id :
Sub-Division Engineer
Name : K.V.Nagabhushana
Designation : AEE
User ID : 2320101
Mobile Number :
Email Id :
Ward Engineer
Name : Srinivas K.S
Designation : Assistant Engineer
User ID : 232010101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Venkatesh.M.S
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :08-06-2009
Commencement Date : 08-06-2009 Probable Date of completion :17-06-2009
Scheduled date of completin as per contract : 00-00-0000 Actual Date of Completion : 17-06-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Work completed