Workcode & Project Details
Work Code Number
: 000-09-N-J-I-R-WD-004
Name of the Project
: Widening and Improvements of Hosur Luskar road
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 245000000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 221200000
Work Order Date
: 19-01-2009
Expenditure Incurred
: 18600000
Client Name
:
Approved Cost in Percentage
: 18
Location Details
District
:
Constituency
:
Zone
: Head Office
Department Type
:
Division
:
Sub Division
:
Ward Name
:
Ward No
:
Locality
:
Postal Code
:
Area
: BTM Layout/Shanthinagar
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2006-07
Budget Category(Head of Account)
: Road related infrastructure P1952
Scheme
: No Scheme
Amount Alloted
:
Administrative Approval No and Date
: UDD-225-MNY-2007 00-00-0000
Technical Sanction No and Date
: CE/MR/TS/144/09-10 00-00-0000
Technical Notification No and Date
: EE/RW/TEND/04/06-07 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: CE Major Roads
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: Sri.Kanakadas/Sri.Ugranarasimhaiah
Designation
: Executive Engineer
User ID
: 23203
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Sri.Narayana Reddy
Designation
: AEE
User ID
: 2320301
Mobile Number
:
Email Id
:
Ward Engineer
Name
: P.Jayram/ Yogesh.H.M
Designation
: Assistant Engineer
User ID
: 232030101
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
: Lakshmi Construction Ltd
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:19-01-2009
Commencement Date
: 19-01-2009
Probable Date of completion
:00-00-0000
Scheduled date of completin as per contract
: 19-07-2009
Actual Date of Completion
: 00-00-0000
Work Status
: Work In Progress
Spill Over / Programme of Work and Year
: Spill Over
Percentage of Physical Progress
: 0
Remarks
: SITE LITEGATION
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 02-05-2024 18:12:14