Workcode & Project Details
Work Code Number
: 000-08-N-J-R-WD-033
Name of the Project
: Providing consultancy Services for Preparation of Detailed Project Report (DPR)for Improvements to Major Road Special (High Density Corridors)
Short Name of Project
:
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 00-00-0000
Estimated Cost
: 5000000
Workcode Approval Date
: 00-00-0000
Approved Cost
: 0
Work Order Date
: 10-12-2008
Expenditure Incurred
: 0
Client Name
:
Approved Cost in Percentage
: 64.71
Location Details
District
:
Constituency
:
Zone
: Head Office
Department Type
:
Division
:
Sub Division
:
Ward Name
:
Ward No
:
Locality
:
Postal Code
:
Area
:
Approval Details
Approved By
:
Year of SR Adopted for Preparation of Estimate
: 2008-09
Budget Category(Head of Account)
: Engineering Project-Consultancy
Scheme
: No Scheme
Amount Alloted
:
Administrative Approval No and Date
: 55/08-09 00-00-0000
Technical Sanction No and Date
: SE(MR)/TS/01/08-09 00-00-0000
Technical Notification No and Date
: EE(MR-Spl)/PR/36/08-09 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: CE Major Roads
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: VIJAY
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: HARISH BABU
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: DEEPA.N.N
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
:
Contractor Name
:
Work Status Details
Agreement No. & Date
: 00-00-0000
Site Handed Over Date
:00-00-0000
Commencement Date
: 00-00-0000
Probable Date of completion
:00-00-0000
Scheduled date of completin as per contract
: 09-03-2009
Actual Date of Completion
: 00-00-0000
Work Status
: Work In Progress
Spill Over / Programme of Work and Year
: Spill Over
Percentage of Physical Progress
: 0
Remarks
: Work Completed and Final Bill to be 0paid
Category Details
Category
:
Type of Work
:
Sub Work
:
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 04-05-2024 08:47:54