Workcode & Project Details
Work Code Number : 000-08-N-J-I-R-AS-080
Name of the Project : Asphalting to Adgodi Road from Bannerghatta road to Hosur Road
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 9970000
Workcode Approval Date : 00-00-0000 Approved Cost : 12729000
Work Order Date : 29-04-2008 Expenditure Incurred : 12498000
Client Name : Approved Cost in Percentage : 0.1495
Location Details
District : Constituency : BTM Layout
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Adugodi Hosur road
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : Road network Arterial and Sub Arterial Roads
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 463/2007-08  00-00-0000
Technical Sanction No and Date : CE(MR)/TS/119/07-08    00-00-0000
Technical Notification No and Date : EE(MR)/TEND/01/07-08  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Umashankar
Designation : Executive Engineer
User ID : 23102
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Basavaraj.R.Kabade 
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Swetha.B
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Suresh.P R
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :29-04-2008
Commencement Date : 29-04-2008 Probable Date of completion :26-07-2008
Scheduled date of completin as per contract : 28-07-2008 Actual Date of Completion : 26-07-2008
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 30-04-2024 08:36:27