logo
Workcode & Project Details
Work Code Number : 000-10-N-P-R-E-WD-033
Name of the Project : Construction of Compound Infront of KPSC property from Park house road to atria hotel in Palace Road
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 728000
Workcode Approval Date : 00-00-0000 Approved Cost : 728000
Work Order Date : 19-08-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 7.28
Location Details
District : Constituency : Shivaji Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Construction of Compound Infront of KPSC property from Park house road to atria hotel
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) :
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : SE/RWC/ADMIN/13/09-10  00-00-0000
Technical Sanction No and Date : EE/RWD/TS/08/09-10  00-00-0000
Technical Notification No and Date : EE/RW/TEND/05/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : T P Padmanaban
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Nagendra Prasad
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Vishwas I k
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :19-08-2009
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 18-09-2009 Actual Date of Completion : 19-09-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 07-05-2024 12:08:15