logo
Workcode & Project Details
Work Code Number : 000-08-N-G-J-R-BB-020
Name of the Project : Construction of Bus Bays at Jyothi School towards City Agara towards Extention Agara towards City Iblur towards City
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2744000
Workcode Approval Date : 00-00-0000 Approved Cost : 2744000
Work Order Date : 28-02-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 18
Location Details
District : Constituency : BTM Layout
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Agara towards Extention Agara towards City Iblur towards City
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : Construction of Bus Bays & Auto Stands
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE/MR/TA/ADM/33/08-09  00-00-0000
Technical Sanction No and Date : SE(MR)/TS/24 /08-09  26-06-2008
Technical Notification No and Date : EE/TEC/TEND/01/07-08  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE Major Roads
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Basavaraj.R. Kabade
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : S D Ashok
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Devaraju Y
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name : Shekar.P
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :30-11-2009
Scheduled date of completin as per contract : 28-03-2009 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Delay due to site problem