Workcode & Project Details
Work Code Number : 000-10-N-J-N-D-FO-029
Name of the Project : Cost Estimate For Construction of Storm Water Drain (MD459) From Backside Sai Baba Ashram to Dakshina Pinakini River (From Ch:749.5m to 1348m)
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 25600000
Workcode Approval Date : 00-00-0000 Approved Cost : 23686040
Work Order Date : 09-10-2009 Expenditure Incurred : 9823977
Client Name : Approved Cost in Percentage : 6.2
Location Details
District : Constituency : Mahadevapura
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Kadugudi
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : CE/SWD/36/2009-10  28-05-2009
Technical Sanction No and Date : CE/SWD/ADMN/36/2009-10  28-05-2009
Technical Notification No and Date : EE/SWD/MPZONE/TEND/03/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-1
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Devendra Naik
Designation : Executive Engineer
User ID : 25103
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Mukunda
Designation : AEE
User ID : 2510301
Mobile Number :
Email Id :
Ward Engineer
Name : Siddarajegowda
Designation : Assistant Engineer
User ID : 251030102
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :09-10-2009
Commencement Date : 09-10-2009 Probable Date of completion :31-12-2010
Scheduled date of completin as per contract : 09-12-2010 Actual Date of Completion : 31-12-2010
Work Status : Work In Progress Spill Over / Programme of Work and Year : Pow  2010-11
Percentage of Physical Progress : 90 Remarks : WALL CONCRETE WORK IN PROGRESS