Work Code Number : 000-09-NJND-F0-076
Name of the Project : Construction of drain from HKBK college to H-300 at Ch:4700 of Hebbal valley P-3
Short Name of Project :
Project Code : Package Code : 3
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2900000
Workcode Approval Date : 00-00-0000 Approved Cost : 0
Work Order Date : 28-02-2009 Expenditure Incurred : 2883000
Client Name : Approved Cost in Percentage : 2900000
Location Details
District : Constituency : Sarvagna Nagaram
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : HKBK college
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE/SWD/AS/246/08-09  00-00-0000
Technical Sanction No and Date : CE/SWD/TS/155/08-09  00-00-0000
Technical Notification No and Date : EE/SGN/TEND/06/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-1
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : H Nagendrappa
Designation : Executive Engineer
User ID : 25101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Ganesh Rao
Designation : AEE
User ID : 2510103
Mobile Number :
Email Id :
Ward Engineer
Name : Jagadisha B R
Designation : Assistant Engineer
User ID : 251010301
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Prabhakar Shetty
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :02-01-2009
Scheduled date of completin as per contract : 27-04-2009 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : FILE SUBMITTED FOR CABINET APPROVAL