logo
Workcode & Project Details
Work Code Number : 000-09-N-J-N-D-FO-067
Name of the Project : CONSTRUCTION OF BOX CULVERTS AT CH 625 675720 & 760 MTS AND BOX DRAIN FROM CH 200 TO 230M IN SECONDARY DRAIN H-103 IN HVP - I
Short Name of Project :
Project Code : Package Code : 1
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 20125000
Workcode Approval Date : 00-00-0000 Approved Cost : 0
Work Order Date : 01-01-2010 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 16.5
Location Details
District : Constituency : Hebbal
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : GIDAPPA BLOCK
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : SWD JNNURM
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : CE/SWD/ADMN/19/09-10  00-00-0000
Technical Sanction No and Date : CE/SWD/TS/17/09-10  00-00-0000
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-1
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : NAGENDRAPPA H
Designation : Executive Engineer
User ID : 25101
Mobile Number :
Email Id :
Sub-Division Engineer
Name : SIDLA BASAPPA
Designation : AEE
User ID : 2510101
Mobile Number :
Email Id :
Ward Engineer
Name : PARAMESHWAR KL
Designation : Assistant Engineer
User ID : 251010101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 30-04-2010 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Excess Budgetry Grants
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 29-04-2024 05:40:55