Work Code Number : 000-09-N-J-N-D-FO-043
Name of the Project : Construction of RCC Retaining wall & SSM Wall frm Ch:613 to 743mtrd for C-203 Secondary SWD in Challagatta Package-1
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 4595000
Workcode Approval Date : 00-00-0000 Approved Cost : 0
Work Order Date : 09-09-2008 Expenditure Incurred : 4585000
Client Name : Approved Cost in Percentage : 14.89
Location Details
District : Constituency : Pulikeshi Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Gandhinagara S.K.Garden Tannoy Road
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE(SWD)/Amin/09/2008-09  00-00-0000
Technical Sanction No and Date : CE(SWD)/ATech-San/34/2008-09  00-00-0000
Technical Notification No and Date : EE(SWD)/CVP/Tend/01/2008-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-1
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri C.Suresh
Designation : Executive Engineer
User ID : 25104
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri N.Nagaraj
Designation : AEE
User ID : 2510401
Mobile Number :
Email Id :
Ward Engineer
Name : Sri R. Nitin
Designation : Assistant Engineer
User ID : 251040101
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :08-12-2008
Scheduled date of completin as per contract : 08-11-2008 Actual Date of Completion : 00-00-0000
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Work completed
Category Details
Category : Type of Work : Sub Work :