Agreement No. & Date : 00-00-0000
|
Site Handed Over Date :27-01-2009
|
Commencement Date : 00-00-0000
|
Probable Date of completion :30-11-2009
|
Scheduled date of completin as per contract : 28-07-2009
|
Actual Date of Completion : 30-11-2009
|
Work Status : Work In Progress
|
Spill Over / Programme of Work and Year : Programme of Work
|
Percentage of Physical Progress : 0
|
Remarks : Construction of 50.00 mtr length of Rcc 'U' shaped is balanced due to protest from site owner .hence completion of Work delayed
|