Work Code Number : 000-10-N-J-N-U-EM-002
Name of the Project : Remo of SWD U/S of BG Road near Ranka Colony Shifting/reallinment of HT/LT cables crossing SWD D/S of Bridge
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 976000
Workcode Approval Date : 00-00-0000 Approved Cost : 976000
Work Order Date : 07-10-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 9.76
Location Details
District : Constituency : Bommanahalli
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Belekahalli/Ranka Colony/BG Road
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : Jnnurm
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : CE/SWD/AS/85/09-10  00-00-0000
Technical Sanction No and Date : CE/SWD/TS/90/09-10  00-00-0000
Technical Notification No and Date : EE/SWD/KV/TEND/05/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Tanveer Ahmed
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : T.Prabhakar
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : M.Venkatesh
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :08-10-2009
Commencement Date : 00-00-0000 Probable Date of completion :07-11-2009
Scheduled date of completin as per contract : 07-11-2009 Actual Date of Completion : 11-11-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Work Completed