Work Code Number : 000-10-N-J-N-D-FO-019
Name of the Project : Construction of RCC U-shape drain from Banashakari to Navodaya Layout which Joins K-210 (frm Ch:0 to 350mts)in Koramangala Valley P-3
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 9910000
Workcode Approval Date : 00-00-0000 Approved Cost : 9910000
Work Order Date : 06-02-2010 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 7.98
Location Details
District : Constituency : Jaya Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Shakabari Nagar Jayanagara
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE/SWD/ADM/37/09-10  13-01-2010
Technical Sanction No and Date :   13-01-2010
Technical Notification No and Date : EE(SWD(/KV/Tend/03/2009-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri Tanvir Ahamed
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Shashidhar
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Venkatesh
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 B (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :06-02-2010
Commencement Date : 06-02-2010 Probable Date of completion :30-01-2011
Scheduled date of completin as per contract : 06-07-2010 Actual Date of Completion : 30-01-2011
Work Status : Work In Progress Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 20 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 03-05-2024 17:34:28