Workcode & Project Details
Work Code Number : 000-09-N-J-N-D-FO-143
Name of the Project : Construction of RCC Retaining wall on LHS frm 5287 to 5299 of K-100 Primary in Koramangala Package-1
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 462000
Workcode Approval Date : 00-00-0000 Approved Cost : 462000
Work Order Date : 01-12-2008 Expenditure Incurred : 357000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Shanthi Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Shantinagara
Approval Details
Approved By : Commissioner
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : CE/SWD/Admin/97/2008-09  21-11-2008
Technical Sanction No and Date : EE(SWD)/KV/Tech-Sanct/16/2008-09  27-11-2008
Technical Notification No and Date : NA  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri Tanveer Ahmed
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri T.Prabhakar
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri M.Venkatesh
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :10-12-2008
Commencement Date : 10-12-2008 Probable Date of completion :00-00-0000
Scheduled date of completin as per contract : 10-02-2009 Actual Date of Completion : 27-12-2008
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 100 Remarks : Work Completed
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 04-05-2024 01:56:48