Work Code Number : 000-09-N-J-N-D-FO-108
Name of the Project : Construction of RCC Box drain along M.C Layout Marenahalli from Upstream of 22nd Main Rd to Upstream of 5th Main Rd in Subbanna Garden VVP-4
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 9950000
Workcode Approval Date : 00-00-0000 Approved Cost : 9950000
Work Order Date : 21-01-2009 Expenditure Incurred : 5200000
Client Name : Approved Cost in Percentage : 15
Location Details
District : Constituency : Govindraja Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Marenahalli
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2007-08
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : CE(SWD)/Amin/796/2008-09  00-00-0000
Technical Sanction No and Date :   00-00-0000
Technical Notification No and Date : EE(SWD)/EE/VV/Tend/13/2008-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri Gurudutt
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri Ravishankar. R.S
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri Vijaka Kumar A.R
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : Manjunath.K.P
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :24-09-2009
Commencement Date : 00-00-0000 Probable Date of completion :23-01-2010
Scheduled date of completin as per contract : 20-07-2009 Actual Date of Completion : 24-09-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Work is in progress