Workcode & Project Details
Work Code Number : 000-09-N-J-N-D-FO-088
Name of the Project : Cont. of RCC Retaining wall on LHS from Ch:5200-5305.0m of K-100 PSWD of KV-1 near Annepaly
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 2468000
Workcode Approval Date : 00-00-0000 Approved Cost : 2468000
Work Order Date : 22-11-2008 Expenditure Incurred : 2056000
Client Name : Approved Cost in Percentage : 1.63
Location Details
District : Constituency : BTM Layout
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Annepalya / LR Slum
Approval Details
Approved By : Commissioner
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : Jnnurm
Scheme : No Scheme
Amount Alloted : Non Budgeted
Administrative Approval No and Date : CE/SWD/adm/58/08-09  30-09-2008
Technical Sanction No and Date : CE/SWD/tech/58/08-09  18-10-2008
Technical Notification No and Date : EE/SWD/KV/TEND/05/08-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWD-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Tanveer Ahmed
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : T.Prabhakar
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : M.Venkatesh
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :24-11-2008
Commencement Date : 22-11-2008 Probable Date of completion :12-10-2008
Scheduled date of completin as per contract : 21-02-2009 Actual Date of Completion : 15-01-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 100 Remarks : Work Completed
Category Details
Category : Type of Work : Sub Work :