Work Code Number : 000-10-N-P-F-R-F0-002
Name of the Project : Construction of Road work from Hosur Main gate to Kudulu Panchayat Chainage 0 Mt to 1000 Mt
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 3564000
Workcode Approval Date : 00-00-0000 Approved Cost : 3564000
Work Order Date : 05-09-2009 Expenditure Incurred : 0
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency :
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Hosur Gate
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2008-09
Budget Category(Head of Account) : Approach road
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : JC(M)/AS/03/09-10  00-00-0000
Technical Sanction No and Date : CE(SWM)/TS/07/09-10  00-00-0000
Technical Notification No and Date : EE-1(SWM)/Tend/03/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : CE SWM
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri Balappa Reddy
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri.K.T.Nagaraj
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri Mujahid Pasha
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 00-00-0000 Probable Date of completion :04-01-2010
Scheduled date of completin as per contract : 04-01-2010 Actual Date of Completion : 04-01-2010
Work Status : Work In Progress Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Work in progress